Environmental clearance

Two judgements of the Supreme Court of India

The Supreme Court of India

On 17 March 2025, the Supreme Court of India delivered two judgements. One was on the appeal of the Auroville Foundation against the verdict of the National Green Tribunal passed in April 2022; the other on the appeal of the Auroville Foundation against the judgement of the Madras High Court of March 2024 regarding the Auroville Town Development Council.

Summaries of the verdict of the National Green Tribunal and of the Chennai High Court judgement, both now dismissed by the Supreme Court

The National Green Tribunal verdict and appeal The Auroville Universal Township Master Plan (Perspective 2025) is a perspective and directional document that was approved in 2001 by the Ministry of Human Resources Development (HRD) – now Ministry of Education (MoE) – and published by the Secretary of the Auroville Foundation in the Gazette of India in 2010.

Concern about bypassing laws

On 19 March, three Residents’ Assembly appointed working groups, the RA-WCom, L’Avenir d’Auroville (RA-TDC) and the Auroville Council, sent a joint letter to the Matrimandir Team and the Auroville Town Development Council constituted by the Governing Board, warning about non-compliance consequences with Indian law, which requires obtaining necessary quarrying permits for ordinary earth excavation and approvals and environmental clearances for the creation of water bodies of the magnitude of the Matrimandir Lake.

Minutes of the 67th Governing Board meeting

In response to a Right to Information request of 7 December, 2024 the Department of Higher Education of the Ministry of Education has sent the applicant on 3 January the minutes of the 67th Governing Board meeting held in Auroville on 31 May, 2024.

The Matrimandir lake controversy

Excavating the next section of the lake

In our July issue, we reported on recent developments on the site of the Matrimandir lake. These included the excavation of section two of the lake, which will be 250 metres long, more than twice the length of the existing test lake.

The National Green Tribunal judgement

On April 28th, 2022, the Southern Bench of the National Green Tribunal (NGT) Chennai, comprising judicial member Justice K. Ramakrishnan and expert member K.